2018 - Technical Training and Certification Program (Scott SWCD)
Marcey Westrick
[Technical Training and Certification 2018] (c) $3,325,000 the first year and $4,275,000 the second year are for accelerated implementation, including local resource protection and enhancement grants and statewide program enhancements of supplements for technical assistance, citizen and community outreach, compliance, and training and certification.
Two trainings will be delivered:
1) Bioretention Design Criteria, Construction Specifications, and Implementation for site-scale stormwater runoff control.
This is a 2-day classroom and field course that will be developed and delivered by Ramsey SWCD; and
2) Basics of Construction Plans Preparation, Supervision, and Documentation. This also a 2-day classroom and field course,
with a self-directed assignment required by each participant in order to receive certification of completion. This training
will be developed and delivered by Scott SWCD
Completed activities as proposed. Basics of Construction Plans Preparation, Supervision, and Documentation training was developed and presented by Scott
SWCD in partnership with BWSR staff on March 6 and 7. Bioretention Design Criteria, Construction Specifications, and Implementation training was developed and presented by Ramsey County/Conservation District on March 15 and April 12.
LOCAL LEVERAGED FUNDS