Judicial Ditch #30 & #18 Buffer Initiative

Project Details by Fiscal Year
2011 Fiscal Year Funding Amount
$93,844
Fund Source
Clean Water Fund
Recipient
Pennington SWCD
Recipient Type
Local/Regional Government
Status
Completed
Start Date
January 2011
End Date
December 2013
Activity Type
Restoration/Enhancement
Counties Affected
Pennington
Pennington
Project Overview

The 14,080 acre watershed of JD#30 and JD#18 drains into the Thief River four miles upstream of Thief River Falls. The City of Thief River Falls draws their drinking water from the reservoir the Thief River supplies. This reservoir is filling with sediment faster than anticipated. It was first estimated that the reservoir would require dredging every 50 years. The last dredging was needed in only 35 years at a price tag of $1.1 million. Treatment of the water for drinking is a major expense to the City. Further downstream, the City of Grand Forks pulls its drinking water from the Red Lake River, making water quality of the Red Lake River a regional concern.The Thief River is impaired for turbidity and low dissolved oxygen. The Red Lake Watershed District has done extensive monitoring of the Thief River Watershed in preparation for the TMDL process. The Pennington SWCD has completed surface water monitoring on JD#30. Hydrologic models indicate a significant reduction in the amount of sediment and phosphorus with the implementation of buffers and grade stabilization structures directly adjacent to the ditch system.The JD#30 and #18 Buffer Initiative will provide incentive payments for landowners to install a 50 foot wide buffer strip and install grade stabilization structures such as side water inlets from field ditches along the 24 mile ditch system. Through this process, the sediment load will be reduced by 80 percent along with a 75 percent reduction in phosphorus.Buffer strips and side water inlets slow down the flow of water. These pipes are sized according to the watershed acres draining towards them. Buffer strips increase infiltration, slow down runoff and prevent normal tillage from depositing chunks of soil in the waterway.

Competitive Grant Making Body
Conflict of Interest Disclosed
No
Conflict of Interest Contact

Nicole Clapp

Legal Citation / Subdivision
Laws of Minnesota 2009, Chapter 172, Article 2, Section 6 (c)
Appropriation Language

(c) $3,000,000 the first year and $3,000,000 the second year are for nonpoint source pollution reduction and restoration grants to watershed districts, watershed management organizations, counties, and soil and water conservation districts for grants in addition to grants available under paragraphs (a) and (b) to keep water on the land and to protect, enhance, and restore water quality in lakes, rivers, and streams, and to protect groundwater and drinking water. The projects must be of long-lasting public benefit, include a local match, and be consistent with TMDL implementation plans or local water management plans. Up to five percent may be used for administering the grants (2011 - Clean Water Assistance)

2011 Fiscal Year Funding Amount
$93,844
Other Funds Leveraged
$23,461
Proposed Measurable Outcome(s)

50 foot buffer strips will help reduce the sediment load by 80 percent along with a 75 percent reduction in phosphorus.

Measurable Outcome(s)

Although the Thief River and Red Lake River are identified as priority resources in local water plans, landowners viewed competing land uses and high commodity prices as a higher priority. A series of letters, individual landowner meetings and other promotion efforts including newsletters and news articles failed to generate interest in this program during the grant period.

Project Manager
First Name
Bryan
Last Name
Malone
Organization Name
Pennington SWCD
Phone
(218) 683-7075
Administered By
Administered by
Location

520 Lafayette Road North
St. Paul, MN 55155

Phone
651- 296-3767